Prepare the application as a coordinated package
If you already know your renovation requires building consent, the next job is not simply:
“Send some plans to council.”
A useful application needs to identify the proposed building work clearly and provide enough information for the building consent authority, or BCA, to assess whether the work would comply with the Building Code if it is completed according to the submitted plans and specifications.
For a homeowner, the practical process is:
Confirm the application route → assemble the current design package → identify who owes each supporting item → check your BCA's local submission requirements → submit → track any request for further information → record the decision → keep the exact issued-consent package before work begins.
If you are still deciding whether building consent is required, use SeekSaver's Building Consent for Renovations NZ first.
Jump to the Building Consent Application Preparation RecordStart with the BCA that will process the application
Section 44 of the Building Act requires the owner to apply for building consent before the relevant building work begins.
The application goes to a BCA authorised to grant consent for the proposed work.
For most homeowners this will involve the relevant local council.
Before assembling the application, check that BCA's current website for:
- its submission system or portal;
- local application guidance;
- local checklists;
- file-format or document-order requirements;
- any project-specific information it asks applicants to provide.
MBIE recommends checking your council's website because local BCAs may have additional submission requirements and different electronic systems.
Do not use an Auckland-specific portal or checklist as if it were the national process.
The owner remains responsible, but someone else can prepare or submit the application
The legal responsibility sits with the building owner.
MBIE says the owner is responsible for applying for building consent where required and providing the necessary information to demonstrate Building Code compliance.
However, that does not mean the homeowner must personally prepare every drawing, calculation or form.
Depending on the renovation, information may come from:
- the owner;
- an authorised applicant or agent;
- designer or architect;
- engineer;
- builder;
- LBP;
- plumber or drainlayer;
- product supplier or manufacturer;
- another project-specific specialist.
Form 2 expressly allows an authorised agent to apply on behalf of the owner.
The practical question is therefore:
Who is responsible for preparing each application item, and is the current version ready?
SeekSaver's application record is designed to track that question.
Drawings
Designer or architect
Specification
Designer or project team
Engineering
Engineer, where required
Product evidence
Supplier or designer, where required
Certificate of Design Work
Relevant LBP, where required
Provider roles vary by project.
If responsibilities are being allocated contractually, also use the Renovation Contract Checklist NZ. The contract can allocate tasks but cannot replace statutory or BCA requirements.
Form 2 is the formal application form
A building consent application must be made in the prescribed form.
For the current national process, that is Form 2: Application for project information memorandum and/or building consent under the Building (Forms) Regulations 2004.
Form 2 currently asks for information including:
- the building and its location;
- owner details;
- agent details where relevant;
- description of the building work;
- relevant existing/project information;
- Building Code compliance information;
- RBW information where applicable;
- specified-system information where applicable;
- relevant attachments.
The current form also reflects the 2026 plumbing and drainlaying self-certification framework where that pathway is being used.
SeekSaver's Building Consent Application Preparation Record does not replace Form 2.
It is only an organisational record to help make sure the real application package is coherent.
What every application needs versus what may depend on the project
Avoid using one enormous universal document checklist.
Section 45 sets the national core requirements.
The application must:
- use the prescribed form;
- include the plans and specifications required by regulations or by the BCA;
- include other information the BCA reasonably requires;
- include applicable fees and charges;
- include additional information required where particular statutory circumstances apply, including retained RBW/CDW and self-certifiable plumbing/drainlaying provisions where relevant.
Beyond that, the exact package depends on the work.
Core application package
At a practical level, establish:
- current Form 2;
- current plans;
- current specifications;
- the Building Code compliance information supporting the proposal;
- project and ownership/agent information;
- any other nationally or locally required application information.
Information that may be required depending on the work
Depending on your renovation, the package may also include:
- structural or engineering calculations and reports;
- geotechnical information;
- product technical information;
- evidence supporting an alternative solution;
- plumbing or drainage information;
- Certificate of Design Work where restricted design work is involved;
- LBP details where RBW is relevant;
- product certification information;
- specified-system information;
- other evidence needed to demonstrate Building Code compliance.
MBIE explains that compliance evidence can include Acceptable Solutions, Verification Methods, calculations, test results, product technical information, certification or appropriate expert evidence depending on the design pathway.
These are examples, not a claim that every renovation application requires every item.
BCA-specific requirements
Your particular BCA may also specify:
- local checklist requirements;
- document order;
- naming conventions;
- submission portal steps;
- local supporting information.
Record these separately from the national statutory requirements.
That distinction helps prevent:
“My friend's council accepted this package, so mine must be complete too.”
Keep one current design package
A common application-management risk is having multiple versions of drawings or specifications circulating at the same time.
Before submitting, identify the exact current:
- drawing set;
- revision/date;
- specification;
- engineering documents;
- product information;
- other supporting reports.
Use one application register to show which version was actually submitted.
If a consultant updates a document while the application is being reviewed, record:
- what changed;
- new version/reference;
- why it changed;
- whether it was sent to the BCA;
- which earlier version it replaces.
This is SeekSaver practical recordkeeping, not a statutory version-control system.
Draft
Submitted version
RFI response version
Issued/approved version
A clear project baseline also matters before documents are coordinated. Use the Home Renovation Project Brief Checklist NZ if the proposed project itself is still undefined.
If Restricted Building Work is involved
Keep this section narrow.
Section 45 requires an application relating to RBW to state the names of licensed building practitioners involved in carrying out or supervising that work, as far as those names are known at application time.
If the submitted design contains design work that is RBW, section 45 also requires the relevant design to have been carried out or supervised by appropriately licensed practitioners and accompanied by a Certificate of Design Work.
Form 2 also provides for RBW/LBP information and notes that practitioner details unknown at application time must be supplied before the work begins.
This page does not determine:
- whether your renovation is RBW;
- which licence class is required;
- whether a particular practitioner is suitable.
Those are separate practitioner questions.
For this application page, simply track whether any required LBP/design information has been identified and supplied.
Resource consent and other approvals remain separate
Having a building-consent application underway does not automatically resolve local planning or other regulatory requirements.
If your project has a separate resource-consent, planning or other approval issue, track that separately.
Do not assume:
“Building consent submitted = every approval is covered.”
Likewise, do not turn Resource #10 into a resource-consent guide.
Check the package before submission
Before submitting, ask:
- Is Form 2 current?
- Is the proposed work described consistently across the documents?
- Are the drawing and specification versions aligned?
- Is each supporting report current?
- Is the Building Code compliance pathway clear enough for the BCA to assess?
- Are project-specific certificates or practitioner details included where required?
- Have you checked the actual BCA's submission guidance?
- Are unresolved items clearly assigned to someone?
MBIE's guidance says a good application should be clear, correct and complete, with a suitable level of detail.
That does not mean SeekSaver can certify an application as legally complete.
Only record:
Ready for submission
when your project team has completed the checks you chose to track.
Submit and record the BCA acknowledgement
Once the application is submitted, record:
- submission date;
- BCA;
- portal or submission method;
- application/reference number;
- acknowledgement received;
- package/version submitted.
Do not treat an automated upload receipt as:
“Building consent accepted.”
MBIE explains that the BCA checks whether an application is complete enough to accept for review. If it is incomplete, missing information may be requested before that review proceeds.
If the BCA expressly tells you that the application has been accepted for review, you can record that procedural status.
Do not assign it yourself.
What the 20-working-day rule actually means
The 20-working-day rule is often misunderstood.
For an ordinary building-consent application, section 48 generally requires the BCA to grant or refuse the application within 20 working days after receiving an application that complies with section 45.
Some specified statutory application types have shorter processing periods.
MBIE describes the ordinary homeowner process as the 20-working-day period running from the BCA receiving a complete application.
That does not mean:
“Your consent is guaranteed to be approved 20 working days after you upload it.”
The outcome can be:
- grant;
- refusal;
- or a request for further information during processing.
The real elapsed time can also be longer where information is missing or the statutory clock is suspended.
- 1.Complete application received
- 2.Statutory processing clock
- 3.RFI issued
- 4.Clock suspended
- 5.Information received
- 6.Processing resumes
- 7.Grant or refusal
20 working days is a statutory processing framework, not guaranteed elapsed time from initial upload to approval.
What happens when the BCA asks for more information?
The BCA may require further reasonable information about the application.
This is commonly called a request for information, or RFI.
When an RFI is made under section 48, the statutory processing period is suspended until the BCA receives the requested information. MBIE describes this as stopping the clock.
Do not treat an RFI as automatic refusal.
Instead, create one record for each request:
- request date;
- exact information requested;
- responsible person;
- any target date actually stated;
- document/version prepared;
- response date;
- response reference;
- whether another question remains open.
A weak or incomplete response can generate further questions.
Your aim is to preserve a clear chain:
BCA question → responsible person → response → exact document/version returned.
How the BCA makes the decision
The BCA does not grant consent because the application simply “looks complete”.
Under section 49(1), a BCA generally must grant building consent if it is satisfied on reasonable grounds that the Building Code would be met if the work were properly completed in accordance with the plans and specifications accompanying the application. If the application relies on the self-certifiable plumbing or drainlaying pathway, section 49(1A) adds separate conditions for that work before the consent may be granted.
This guide does not explain eligibility for plumbing or drainlaying self-certification. It only records the narrow application-processing qualification that applies where that pathway is being used.
That is why the supporting evidence matters.
Depending on the project, assessment can involve different building disciplines and technical information.
Some specific application types may also involve Fire and Emergency New Zealand under sections 46–47. That is not a universal step for ordinary renovation applications.
If the building consent is granted
Grant is the BCA's statutory decision.
The issued building consent then becomes the regulatory package you need to work from.
Before physical building work begins, keep the exact issued package, including:
- issued building consent;
- approved plans;
- approved specifications;
- attached documents;
- conditions or notes;
- relevant consent reference and date.
Do not keep working from an earlier submitted drawing set if the issued documents differ.
Make sure the relevant project team receives the approved versions.
A building consent normally lapses if building work does not commence within 12 months after issue, unless the BCA allows a further period.
This article stops here.
It does not teach construction inspections, later consent amendments or CCC.
If the application is refused
Section 50 requires the BCA to give the applicant written notice of:
- the refusal; and
- the reasons for refusal.
Record:
- decision date;
- BCA reference;
- written notice;
- stated reasons;
- documents affected;
- who needs to review the reasons;
- next project action.
Do not assume refusal means:
- the BCA acted unlawfully;
- the design can never be consented;
- one particular legal remedy applies.
The next step depends on the reasons and the project.
Where necessary, ask the BCA, designer, engineer or appropriate adviser what information or design work needs to be reconsidered.
Building Consent Application Preparation Record
Use this record to organise the application from preparation to the issued-consent package.
It is designed to answer:
- What does the application need?
- Who provides it?
- Which version is current?
- What did we submit?
- What has the BCA asked for?
- What remains unresolved?
- What exact consent package was eventually issued?
It does not submit the application or decide whether it complies with the Building Act or Building Code.